Transformer Slide (NES)
Sentry was contracted to offload a 180,000-lb transformer and safely set it onto its foundation pad at a Nashville, TN substation. Using the jack-and-slide system, the crew precisely aligned and positioned the unit within tight tolerances while maintaining full control of load movement and site safety.
Division: Machinery Moving
Location: Nashville, TN
Client / General Contractor: Nashville Electric Service
Project Type: Industrial (Commercial, Industrial, Institutional, etc.)
Scope of Work: Offload, jack, and slide onto pad (180,000 lbs.)
Start Date: August 2025
Completion Date: August 2025
Project Size: 180,000 lb. transformer (square footage, tonnage, or number of units, etc.)
Equipment Used: 300 ton HT jack and slide system (key cranes, forklifts, rigging systems, etc.)