BNA Concourse D Extension

Sentry erected 1,667 tons of structural steel, including complex roof and floor framing, rotunda and concourse steel, braced and moment frames, and extensive miscellaneous metals. The work was completed with precise sequencing and tight-site coordination at Nashville International Airport (BNA), which welcomed a record-breaking 24.7 million passengers in FY 2024–25—its busiest year ever and a milestone for one of the nation’s fastest-growing airports.

Division: Steel
Project Name: MNAA Concourse D Extension
Location: Nashville, TN
Client / General Contractor: Hensel Phelps Construction Co.
Project Type: Commercial (Commercial, Industrial, Institutional, etc.)
Scope of Work: Erection of structural + miscellaneous steel}
Start Date: March 2024
Completion Date: February 2025
Project Size: 1,667 tons of structural steel + miscellaneous steel (square footage, tonnage, or number of units, etc.)
Equipment Used: (Key cranes, forklifts, rigging systems, etc.) — not specified